Newly-built ventilation, air conditioning, heating and smoke extract plant in the power plant cavern and transformer cavern, located in Limberg II
Outside air 15,000 m³/h, smoke extract 50,000 m³/h, cooling capacity ca. 900 kW, invest ca. 1.3 Mio €
Client
VERBUND-Austrian Hydro Power AG
Field
Energy supplier
Task
Review of planning and tendering, replanning and new tendering, KKS-labelling, verification of building plans
Period of time
Planning started in October 2007, initial operation in August 2010